DPD Permit Turnaround Times, Mar. 2010
DPD is committed to providing good customer service to its applicants. The permit turnaround data is updated monthly online and can be viewed at www.seattle.gov/dpd/resourcecenter (go to “Turnaround/Approval Times 2010“).
|
Type of Permit
|
Goal
|
Mar. 2010 Performance
|
| Simple Building IP* | 80% in 48 Hours | 95.8% |
| Medium Construction IP | 80% in 2 Weeks | 85.0% |
| Complex Construction IP | 70% in 6 Weeks | 84.1% |
| Construction Issuance | 90% in 120 Days | 76.4% |
| Master Use Permit Decisions | 80% in 120 Days | 81.4% |
Posted: May 4th, 2010 under Building Connections, Customer Alerts, dpdINFO Newsletter.
Tags: Permit Pipeline Newsletter, turnaround times