DPD is committed to providing good customer service to its applicants. The permit turnaround data is updated monthly online and can be viewed at www.seattle.gov/dpd/resourcecenter (go to “Turnaround/Approval Times 2013“).
Type of Permit |
Goal |
Mar. 2013 Performance |
Simple Building IP* |
80% in 48 Hours |
93.1% |
Medium Construction IP |
80% in 2 Weeks |
30.4% (82.1% in 3 weeks) |
Complex Construction IP |
80% in 8 Weeks |
77.5% |
Construction Issuance |
90% in 120 Days |
94.9% |
Master Use Permit Decisions |
80% in 120 Days |
84.3% |
*IP: Initial Plan Review by DPD staff