DPD is committed to providing good customer service to its applicants. The permit turnaround data is updated monthly online and can be viewed at www.seattle.gov/dpd/toolsresources/ (go to “Turnaround / Approval Times 2013”).
Type of Permit | Goal | April 2013 Performance |
Simple Building IP* | 80% in 48 Hours | 97.5% |
Medium Construction IP | 80% in 2 Weeks | 61.8% (92.1% in 3 wks) |
Complex Construction IP | 80% in 8 Weeks | 79.4% |
Construction Issuance | 90% in 120 Days | 93.2% |
Master
Use Permit Decisions |
80% in 120 Days | 73.5% |
*IP: Initial Plan Review by DPD staff