DPD is committed to providing good customer service to its applicants. The permit turnaround data is updated monthly online and can be viewed at www.seattle.gov/dpd/toolsresources/ (go to “Turnaround / Approval Times 2014”).
Type of Permit | Goal | Mar. 2014 Performance |
Simple Building IP* | 80% in 48 Hours | 97.2% |
Medium Construction IP | 80% in 2 Weeks | 62.8% |
Complex Construction IP | 80% in 8 Weeks | 59.1% |
Construction Issuance | 90% in 120 Days | 86.5% |
Master Use Permit Decisions | 80% in 120 Days | 91.4% |
*IP: Initial Plan Review by DPD staff