Seattle DCI is committed to providing good customer service to its applicants. The permit turnaround data is updated monthly online and can be viewed at www.seattle.gov/dpd/toolsresources/ (go to “Turnaround / Approval Times”).
Type of Permit | Goal | Jan. 2016 Performance |
Simple Building IP* | 80% in 48 Hours | 99.6% |
Medium Construction IP | 80% in 2 Weeks | 18.5% (26.8% in 3 wks) |
Complex Construction IP | 80% in 8 Weeks | 60.5% |
Construction Issuance | 90% in 120 Days | 96.6% |
Master Use Permit Decisions | 80% in 120 Days | 82.3% |
*IP: Initial Plan Review by Seattle DCI staff