We are committed to providing good customer service to its applicants. The permit turnaround data is updated monthly online and can be viewed atwww.seattle.gov/dpd/toolsresources/ (go to “Turnaround / Approval Times”).
Type of Permit | Goal | July 2016 Performance |
Simple Building IP* | 80% in 48 Hours | 96.20% |
Medium Construction IP | 80% in 2 Weeks | 53.87% |
Complex Construction IP | 80% in 8 Weeks | 72.37% |
Construction Issuance | 90% in 120 Days | 89.48% |
Master Use Permit Decisions | 80% in 120 Days | 80.65% |
*IP: Initial Plan Review by Seattle DCI staff