We are committed to providing good customer service to our applicants. The permit turnaround data is updated monthly online and can be viewed at www.seattle.gov/dpd/toolsresources/ (go to “Turnaround / Approval Times”).
Type of Permit | Goal | Oct. 2017 Performance |
Simple Building IP* | 80% in 48 Hours | 91.1% |
Medium Construction IP | 80% in 2 Weeks | 66.2% |
Complex Construction IP | 80% in 8 Weeks | 74.7% |
Construction Issuance | 90% in 120 Days | 88.0% |
Master Use Permit Decisions | 80% in 120 Days | 46.7% |
*IP: Initial Plan Review by SDCI staff