We are committed to providing good customer service to our applicants. The permit turnaround data is updated monthly online and can be viewed at www.seattle.gov/dpd/toolsresources/ (go to “Turnaround / Approval Times”).
Type of Permit | Goal | Feb. 2018 Performance |
Simple Building IP* | 80% in 48 Hours | 97.1% |
Medium Construction IP | 80% in 2 Weeks | 30.5% |
Complex Construction IP | 80% in 8 Weeks | 50.0% |
Construction Issuance | 90% in 120 Days | 84.7% |
Master Use Permit Decisions | 80% in 120 Days | 61.2% |
*IP: Initial Plan Review by SDCI staff