DPD is committed to providing good customer service to its applicants. The permit turnaround data is updated monthly online and can be viewed at www.seattle.gov/dpd/resourcecenter (go to “Turnaround/Approval Times 2010“).
Type of Permit
|
Goal
|
Mar. 2010 Performance
|
Simple Building IP* | 80% in 48 Hours | 95.8% |
Medium Construction IP | 80% in 2 Weeks | 85.0% |
Complex Construction IP | 70% in 6 Weeks | 84.1% |
Construction Issuance | 90% in 120 Days | 76.4% |
Master Use Permit Decisions | 80% in 120 Days | 81.4% |