DPD is committed to providing good customer service to its applicants. The permit turnaround data is updated monthly online and can be viewed at www.seattle.gov/dpd/resourcecenter (go to “Turnaround/Approval Times 2010“).
Type of Permit | Goal | Sept. 2010 Performance |
Simple Building IP* | 80% in 48 Hours | 81.44% |
Medium Construction IP | 80% in 2 Weeks | 20.70% |
Complex Construction IP | 70% in 6 Weeks | 73.24% |
Construction Issuance | 90% in 120 Days | 94% |
Master Use Permit Decisions | 80% in 120 Days | 91.67% |
*IP: Initial Plan Review by DPD staff