DPD is committed to providing good customer service to its applicants. The permit turnaround data is updated monthly online and can be viewed at www.seattle.gov/dpd/resourcecenter (go to “Turnaround/Approval Times 2010“).
Type of Permit | Goal | Nov. 2010 Performance |
Simple Building IP* | 80% in 48 Hours | 92.6% |
Medium Construction I | 80% in 2 Weeks | 31.7% |
Complex Construction IP | 70% in 6 Weeks | 66.1% |
Construction Issuance | 90% in 120 Days | 95.4% |
Master Use Permit Decisions | 80% in 120 Days | 88.5% |
*IP: Initial Plan Review by DPD staff