DPD is committed to providing good customer service to its applicants. The permit turnaround data is updated monthly online and can be viewed at www.seattle.gov/dpd/resourcecenter (go to “Turnaround/Approval Times 2011“).
Type of Permit | Goal | April 2011 Performance |
Simple Building IP* | 80% in 48 Hours | 86.8% |
Medium Construction IP | 80% in 2 Weeks | 45.6% |
Complex Construction IP | 70% in 8 Weeks | 82.1% |
Construction Issuance | 90% in 120 Days | 94.8% |
Master Use Permit Decisions | 80% in 120 Days | 79.2% |
*IP: Initial Plan Review by DPD staff