DPD is committed to providing good customer service to its applicants. The permit turnaround data is updated monthly online and can be viewed at www.seattle.gov/dpd/resourcecenter (go to “Turnaround/Approval Times 2011“).
Type of Permit
|
Goal
|
July 2011 Performance
|
Simple Building IP*
|
80% in 48 Hours
|
90.9%
|
Medium Construction IP
|
80% in 2 Weeks
|
67.3%
|
Complex Construction IP
|
70% in 8 Weeks
|
93.0%
|
Construction Issuance
|
90% in 120 Days
|
96.7%
|
Master Use Permit Decisions
|
80% in 120 Days
|
85.7%
|
*IP: Initial Plan Review by DPD staff