DPD is committed to providing good customer service to its applicants. The permit turnaround data is updated monthly online and can be viewed at www.seattle.gov/dpd/resourcecenter (go to “Turnaround/Approval Times 2011“).
Type of Permit |
Goal |
Mar. 2012 Performance |
Simple Building IP* |
80% in 48 Hours |
98.5% |
Medium Construction IP |
80% in 2 Weeks |
77.9% |
Complex Construction IP |
80% in 8 Weeks |
81.4% |
Construction Issuance |
90% in 120 Days |
83.5% |
Master Use Permit Decisions |
80% in 120 Days |
86.2% |
*IP: Initial Plan Review by DPD staff