DPD is committed to providing good customer service to its applicants. The permit turnaround data is updated monthly online and can be viewed at www.seattle.gov/dpd/toolsresources/ (go to “Turnaround / Approval Times 2013”).
Type of Permit | Goal | Oct. 2013 Performance |
Simple Building IP* | 80% in 48 Hours | 91.5% |
Medium Construction IP | 80% in 2 Weeks | 91.5% |
Complex Construction IP | 80% in 8 Weeks | 87.4% |
Construction Issuance | 90% in 120 Days | 90.9% |
Master Use Permit Decisions | 80% in 120 Days | 81.5% |
*IP: Initial Plan Review by DPD staff