November 2012 Permit Turnaround Times
DPD is committed to providing good customer service to its applicants. The permit turnaround data is updated monthly online and can be viewed at www.seattle.gov/dpd/resourcecenter (go to “Turnaround/Approval Times 2012“).
|
Type of Permit |
Goal |
Nov. 2012 Performance |
|
Simple Building IP* |
80% in 48 Hours |
86.2% |
|
Medium Construction IP |
80% in 2 Weeks |
32.0% (82.6% in 3 weeks) |
|
Complex Construction IP |
80% in 8 Weeks |
84.2% |
|
Construction Issuance |
90% in 120 Days |
95.2% |
|
Master Use Permit Decisions |
80% in 120 Days |
66.0% |
*IP: Initial Plan Review by DPD staff
Posted: January 2nd, 2013 under Building Connections, dpdINFO Newsletter.